Week 6: 09/27 - 10/03

On 10/01:

  • Team members met in person in the library to work on:
    • The team blog
    • Discuss future plans of the project
    • Work on motor requirements for other groups
    • Discussing motor options for bogie
Future plans execution:
  • Gather information of desired motor specs
  • Finding sponsors to fund the motor
  • Place order in for hub motor
  • Decide on the motor (6 hub motors) 
  • Redesign the housing of the motor to fit better on the bogie
  • Finalize on designs.
  • Assembly and Manufacture.
  • Finalize products on the bogie
  • Makers Faire

Comments

  1. High Density Power Motor Team... you have 4 team members on your team, so I expect you would have some more work done by now, however, I know that some last minute changes may have affected your overall progress. I expect you will need to help your Bogie Integration team with some extra hands in regards to design work and fabrication.

    What are your future plans that you discussed?
    What are the motor requirements you developed based on the load of the bogie, friction, and other factors such as power requirements.

    Please be more detailed in future posts.

    ReplyDelete

Post a Comment

Popular posts from this blog

Week 7: 10/03 - 10/10

2nd Semester Week 12: 4/24 - 5/1